In March 2012,the Hampden Township Sewer Authority initiated a sewer extension project to serve Trindle Road.  Since then, sanitary main line and lateral installation has been installed from west of South Sporting Hill Road to the Mechanicsburg Borough line.

Update- June 10, 2013 - Following is Pennsy Supply’s schedule for paving Fetrow Drive and Sheely Lane and the portion of Trindle Road between Sheely Lane and S. Sporting Hill Road:`

  • Trindle Road wearing course is scheduled for Tuesday, June 18th.
  • Paving of the wearing course is scheduled for Fetrow Drive & Sheely Lane on Wednesday, June 12th.

Limited lane closures and limited access to properties may occur during this phase of the project.   If you have further questions about the resurfacing project, please call Scott Minarch, PennDOT Project Manager, at 766-3162.