Main Office : (717)761-0119 |  Utility Department 909-7145 |  Recreation Department: 761-4951 | Police (Non-Emergency): 761-2609

 


Boards/Commissions

 

 


General Information

 

 


Online Forms/Publications

 

 


Township Services

 





Staff:

Superintendent
Diane Fox

Operations Supervisor
Jeff Klahre

Plant Operators
Will Fake

Ken Good

Biosolids Technicians

John Geiling

Nick Stouffer


Pump Station Foreman
Tom Fealtman

Pump Station Technician

Mike Orris


I/I Foreman

Thom Kautz

TV Truck Operators

Greg Bilger

Andy Morales

Flush Truck Operators
Kevin Danner

Lee Timmons

Wastewater Division

4202 Roth Lane

Mechanicsburg, PA  17050

Superintendent: Diane Z. Fox         

Operations Supervisor: Jeffrey Klahre

Staff:

Plant Operator: Ken Good         

Plant Operator: Wilbur Fake

Inflow/Infiltration Foreman: Thom Kautz     

Pump Station Foreman: Tom Fealtman

Collection System Technician: Mike Orris

TV Truck Operator: Greg Bilger       

TV Truck Operator: Andrew Morales

Flush Truck Operator: Kevin Danner     

Flush Truck Operator: Henry Lee Timmons

Biosolids Technician: John Geiling       

BiosolidsTechnician: Charles Stouffer

 

The sewer system consists of approximately 180 miles of collection lines, 23 pumping stations, force mains, and a wastewater treatment plant with a budget of $10.3 million

 

Listed below are the Wastewater Department's major accomplishments in 2010 :

Administrative Tasks Completed

•  Two sections of mainline and two manhole castings were replaced prior to PennDOT repaving the Carlisle Pike.

•  A manhole in the right of way of Creekview Road was relined

•  Substantial completion was achieved on the upgrades to the Roth Lane WWTP and the abandonment of the Pinebrook WWTP

•  Construction has begun on the upgrades of Pumping Station 4, 16 and 19.

•  Gannett Fleming, the Hampden Township Sewer Authority's Consulting Engineer, has begun the Basis of Design for Pumping Station 3, 7, 17 and 18

 

Operational and Maintenance Tasks Completed in 2010

•  Flushed and cleaned over 2.2 miles of main lines in known trouble areas.

•  Cleaned and televised over 6.5 miles of sanitary main lines.   

•  Air tested 812 feet of new main line.

•  Tested 2,297 pipe joints and sealed 351 pipe joints using 216 gallons of grout.

•  Televised and inspected 334 laterals.

•  Utilized the high pressure flush truck to remove roots out of 115 laterals.

•  Replaced three laterals due to root infiltration.

•  Worked with the Public Works Maintenance Division on the Gale Road project to replace 260 feet of eight-inch sanitary mainline and seven laterals.

•  Installed 28 manhole inserts, inspected 102 manholes and raised the casting on 2 manholes.

•  Flushed and televised storm drains for Public Works Maintenance Division.

•  Completed 2,840 locations request by PA One Call

Safety Training 2010

•  Right to Know Training - Snow Plow Training - Trenching and Shoring Training